Fiberglass swimming pool installation is one of the fastest options available, typically completing in 4 to 6 weeks from excavation to your first swim. Key timelines include:

  • Site preparation and excavation: 1-2 weeks
  • Pool delivery, backfilling, and mechanical: 1-2 weeks
  • Coping and Hardscape: 1-2 weeks
  • Final Inspection: 1 week

Variables like weather, permits and inspections, or soil conditions, and site access may impact this timeline.